I want to connect an additional tap – how does that work with a push-fit system?
This is how it works with GF iFIT: at an accessible point of the existing pipe you branch off with a tee module, bridge the run to the new draw-off point with d16 pipe, and at the destination there is a tap connection module or a transition module with ½ female thread for the angle valve or draw-off valve. Every joint: chamfer, calibrate, push, check – without a press tool, without a flame.
The project in one picture
Three points determine the plan: where you branch off (an accessible point of the cold and, if applicable, hot water pipe – basement, ducts, pre-wall), how the pipe runs (every change of direction an elbow module or a hand bend within the permissible radius) and how it ends (wall plate for the tap or transition module with thread). If the existing pipe is not iFIT pipe, a transition goes at the start – which one is explained on transitions to other systems.
The steps
- Shut off the water and drain the pipe – at the pipe’s shut-off valve or at the house connection.
- Prepare the branch point: cut the existing pipe at the branch point and prepare both ends for the tee module – chamfer and calibrate iFIT pipe, fit the matching transition on existing pipe.
- Push on the tee module: adapters onto both pipe ends up to the stop (inspection window filled), push the tee module on until it clicks.
- Lay the run: cut d16 pipe to length, one elbow module per change of direction or a hand bend within the permissible radius; pipe in conduit where it will later be inaccessible.
- Set the end point: fix and push on the tap connection module (wall plate) – or a transition module with ½ female thread for angle valve or draw-off valve.
- Pull-back test at every joint – up to 5 mm of slide is permissible according to GF.
- Leak test before closing wall or pre-wall – fill, vent, test, record.
Every action in detail, with pictures and typical faults: step-by-step installation.
What you need
The rule of thumb: one tee module for the branch, one elbow module per change of direction, pipe length equals run plus 10 % reserve, one transition module per connection to the existing installation – and one adapter for every push point. With the first order the tool set is added: according to the manufacturer, pipe shears and chamfering/calibrating tool belong to every first order – we include them in the enquiry if you do not have them yet.
The exact list with items and availability is worked out by the parts-list tool – enter the dimensions, check the list, send it straight away as an enquiry.
The limits of this project
Cold and hot drinking water up to 70 °C and 10 bar (manufacturer information). The branch belongs at an accessible point, and before closing comes the leak test. The generally recognised rules of technology apply to drinking-water installation – the test values are specified by the planner.
When another route is better
If you branch off a metal pipe without a usable thread, a press transition of the existing system is often the shorter route – one fitting fewer, one sealing point fewer. The overview of the routes: transitions to other systems; the comparison of the methods is on methods compared.
Parts for this project from stock
Send us the parts list from the tool or tell us run and connections – we put together tee module, pipe, adapters and tool set, also individually packed.
Send an inquiryYour inquiry to Zickwolff
Send us what you have – designation, standard, quantity, date. We will clarify the rest with you.
One item or a question
Send inquiry
Not in stock? We procure it – single items too.
Designation, standard and quantity are enough.
Several items
Send bill of materials
200 items? One parts list is enough – we deliver complete.
Attach it as a file.
Helpful if already known: project and country, date needed, certificates, packaging and language of the packing lists. If anything is missing, we will ask.
It is urgent
Request express
When do you need it? Express delivery, to the site if required.
Tell us by when you need the material – we will tell you what is possible.
Technical basis: GF iFIT brochures (2022, 12/2023), GF practice guide for installation and repair instructions (08/2026), GF iFIT product range (07/2025) – authorised-dealer material, use approved. Test values as specified by the planner. Information without guarantee – the binding approval remains with the manufacturer.